CT Insider: Hamden residents have waited 40 years for Six Lakes cleanup. Now they face at least eight more

Four decades after first agreeing to clean up the heavily contaminated Six Lakes property in southern Hamden, its owner now has at least eight more years to finish the job.

Full remediation of the 102.5-acre parcel – which many residents hope will eventually become a state park – must be completed by July 2034, according to a project schedule approved last week by the state Department of Environmental Protection

The property’s owner, Missouri-based Olin Corp., has until July 2029 to determine the full extent of contamination at the site, where officials have already identified at least seven “areas of concern,” according to DEEP. The company must then submit a detailed cleanup plan to DEEP and complete the work by the 2034 deadline.

But Olin can seek an extension if it shows it is making “best efforts” to meet its obligations, DEEP said in its June 16 approval letter. The agency can approve, reject or modify any revised schedule put forth by Olin.

The updated timeline has frustrated several Hamden residents and officials, who say the cleanup has dragged on for too long and who question whether the state will hold Olin to its decades-old promise to restore the property, also known as Pine Swamp and Olin Powder Farm.

“Too long! It’s been 40 years!” one resident shouted Wednesday night as DEEP staff presented the project timeline during a community meeting at the Keefe Community Center. Hamden Mayor Adam Sendroff and state Reps. Laurie Sweet, D-Hamden, and Steve Winter, D-New Haven, also attended.

Read the full story here!

Read more

New Haven Independent: Olin Keeps Testing Six Lakes — And Community Patience

Six Lakes organizer Justin Farmer: “The last time Olin got something in on time was before I existed.” Credit: Brian Slattery photo

John Duff, an environmental analyst at the state’s Department of Energy and Environmental Protection (DEEP), was rounding up his summary of the testing the Olin Corporation has so far conducted at the Six Lakes site in southern Hamden, to figure out how polluted it is in order to make a plan to remediate it.

It was part of DEEP’s annual community meeting, held at the Keefe Community Center on Pine Street in Hamden Wednesday evening, to inform the public regarding the status of the cleanup. Several dozen people attended.

“A very large quantity of data has been obtained over the past few years,” Duff said. But “you got to understand that this is a 102-acre property, and additional characterization is still required for both known and potential areas of concern.”

“Too slow,” a community member interjected. “It’s been 40 years.”

That was the tone of the meeting about Six Lakes, a.k.a. the Powder Farm, a.k.a the Pine Swamp, a 102.5-acre parcel of land and water — bordered by Treadwell Street, Leeder Hill Drive, Putnam Avenue, and the Farmington Canal Trail — with a complex history (read about that here).

Read the full article here

Read more